Downtown Water Line Improvement Updates
We are continuing construction in the project area. Progress has been delayed because of a significant amount of precise hand digging that must be performed between the road and sidewalk. Construction should be completed by March. We apologize for the delay, but we thank the community for their continued patience.
Our contractor will regularly visit residents in the area, but you may always contact Matthew Brady at matthewb@bjwsa.org or 987.9213 for any questions you have about the project.
The project is part of BJWSA's Capital Improvement Program, and is intended improve the delivery of drinking water to the area.
Please visit this page for updates as they become available.